Processing math: 100%
 
+0  
 
+1
28
2
avatar+2729 

Five workers have been hired to complete a job.  If one additional worker is hired, they could complete the job $8$ days earlier.  If the job needs to completed $28$ days earlier, how many additional workers should be hired?

 Mar 3, 2024

Best Answer 

 #2
avatar+130477 
+1

Let the time to complete the job with 5 workers = T days

 

So......the total man-days for the job  is  5T

 

If one additional worker is  hired, the man-days for the job is 6 (T - 8)

 

So....since the man-days will be the same for the job.....

 

5T  = 6(T - 8)

 

5T = 6T - 48

 

48 = T 

 

So   the number of man-days to complete the job is   5(48)  = 240

 

So.....to complete the job 28 days earlier

 

(number of  workers needed) * ( 48 - 28)  =  240

 

(number of workers needed)  * (20)   = 240

 

number of workers needed  = 240 / 20     =    12

 

So.....(12  - 5) =  7  additional workers should be hired to  complete the job 28 days earlier

 

cool cool cool

 Mar 4, 2024
edited by CPhill  Mar 5, 2024
 #1
avatar+15076 
+1

How many additional workers should be hired?

Hello Lilliam0216!

 

I assume the 5 workers can complete the job in around 120 hours.

ψ=J5120hJ=5120hψ=(5+1)(1208)ψ=(5+x)(12028)ψ6112=(5+x)92672=460+92xx=67246092=2.336t=(5+3)92

 

t=8926=12223h

 

If the 5 workers completed the work in 122 2/3 hours, 3 additional workers should be hired to save 28 hours.

An additional time specification is absolutely necessary for your question.

 

laugh  !

 Mar 4, 2024
 #2
avatar+130477 
+1
Best Answer

Let the time to complete the job with 5 workers = T days

 

So......the total man-days for the job  is  5T

 

If one additional worker is  hired, the man-days for the job is 6 (T - 8)

 

So....since the man-days will be the same for the job.....

 

5T  = 6(T - 8)

 

5T = 6T - 48

 

48 = T 

 

So   the number of man-days to complete the job is   5(48)  = 240

 

So.....to complete the job 28 days earlier

 

(number of  workers needed) * ( 48 - 28)  =  240

 

(number of workers needed)  * (20)   = 240

 

number of workers needed  = 240 / 20     =    12

 

So.....(12  - 5) =  7  additional workers should be hired to  complete the job 28 days earlier

 

cool cool cool

CPhill Mar 4, 2024
edited by CPhill  Mar 5, 2024

0 Online Users